Road Closure: Rorrington to Priest Weston
Start Date: 22nd August 2022
End Date: 9th September 2022
Purpose: Construct new retaining wall and kerbing works. Work to be carried out during normal working hours and with reasonable access. • Excavate and remove existing kerbs and retaining wall and dispose Works will take place as follows and the road closure will be in place 24/7 with works taking place between 07:00-17:00: 22/08/2022-26/08/2022 30/08/2022-02/09/2022 05/09/2022-09/09/2022
Works Promoter: Shropshire Council
Works Promoter Ref: UJ215HW-1727117